Henderson Bridget Project Update - Nov. 5, 2021

Henderson Bridge, East Providence/Providence

Steel girder demolition of two bridge spans over the Seekonk River will require the daytime closure of East River Street on Monday, November 8, 2021. Please follow the signed detour. We also plan to continue working on the new realignment and installing a new water main and light base foundations along Waterfront Drive and installing rebar at the east abutment footing and temporary supports at one of the piers.